Landscaping and furnishing of the basement of the church of the Holy Mother of God in Stepanakert

The church of the Holy Mother of God in Stepanakert of the Artsakh Diocese has a large basement, which served as a refuge for people during the last Artsakh war.

The room was not previously used, but served mainly as a warehouse.

We plan to improve and furnish this building with appropriate means so that it serves the spiritual, pastoral and preaching purposes of the Artsakh Diocese.

If the premises are suitable, meetings of the youth union, the women's union of the Holy Mother of God, as well as spiritual social events will be held there.

The premises will also serve for the Center for Christian Education and Propaganda of the diocese:

  • Implementation of spiritual, socio-psychological, religious-moral, national-spiritual, Christian propaganda activities with various social groups in the Republic of Artsakh,
  • organization of spiritual film screenings and discussions,
  • to create conditions in the indicated premises so that during the liturgy mothers with young children participating in the liturgy can leave their children in the care of a nanny or educator so that they can fully participate in the liturgy,
  • one of the rooms adjacent to the basement will become the diocese's library, which is currently not functioning due to lack of sufficient comfortable space,
  • organize youth spiritual and religious intellectual contests and games,
  • organize spiritual singing lessons,
  • organize training of national dances,
  • etc.

Financial expenses for the improvement and furnishing of the basement of the church of the Holy Mother of God in Stepanakert amount to  AMD 7,530,000:

ESTIMATE

Furnishing and operation of the basement of the church of the Holy Mother of God

Name Cost Amount Sum
Wooden door 200 000 6 1 200 000
Door installation 15 000 6 90 000
Iron/soft chairs 15 000 100 1 500 000
Transportation of chairs from Yerevan 150 000 1 150 000
Lighting 300 000 1 300 000
Audio Electronics 1 122 500 1 1 122 500
Projector 838 000 1 838 000
Installation of the projector and lighting fixtures on the ceiling and walls 100 000 1 100 000
Tribune 200 000 1 200 000
Microphone for wired case 100 000 5 500 000
Flag 60 000 2 120 000
Carpet 190 000 2 380 000
Path 13 000 13 169 000
Synthesizer 500 000 1 500 000
Unplanned expenses 360 500 1 360 500
Total 7 530 000

Expenditures of the Ministry of Urban Development currently carried out

Basement ventilation and general heating system of the church 9 000 000 1 9 000 000
WP Radio
WP Radio
OFFLINE LIVE