Landscaping and furnishing of the basement of the church of the Holy Mother of God in Stepanakert

The church of the Holy Mother of God in Stepanakert of the Artsakh Diocese has a large basement, which served as a refuge for people during the last Artsakh war.

The room was not previously used, but served mainly as a warehouse.

We plan to improve and furnish this building with appropriate means so that it serves the spiritual, pastoral and preaching purposes of the Artsakh Diocese.

If the premises are suitable, meetings of the youth union, the women's union of the Holy Mother of God, as well as spiritual social events will be held there.

The premises will also serve for the Center for Christian Education and Propaganda of the diocese:

  • Implementation of spiritual, socio-psychological, religious-moral, national-spiritual, Christian propaganda activities with various social groups in the Republic of Artsakh,
  • organization of spiritual film screenings and discussions,
  • to create conditions in the indicated premises so that during the liturgy mothers with young children participating in the liturgy can leave their children in the care of a nanny or educator so that they can fully participate in the liturgy,
  • one of the rooms adjacent to the basement will become the diocese's library, which is currently not functioning due to lack of sufficient comfortable space,
  • organize youth spiritual and religious intellectual contests and games,
  • organize spiritual singing lessons,
  • organize training of national dances,
  • etc.

Financial expenses for the improvement and furnishing of the basement of the church of the Holy Mother of God in Stepanakert amount to  AMD 7,530,000:

ESTIMATE

Furnishing and operation of the basement of the church of the Holy Mother of God

NameCostAmountSum
Wooden door200 00061 200 000
Door installation15 000690 000
Iron/soft chairs15 0001001 500 000
Transportation of chairs from Yerevan150 0001150 000
Lighting300 0001300 000
Audio Electronics1 122 50011 122 500
Projector838 0001838 000
Installation of the projector and lighting fixtures on the ceiling and walls100 0001100 000
Tribune200 0001200 000
Microphone for wired case100 0005500 000
Flag60 0002120 000
Carpet190 0002380 000
Path13 00013169 000
Synthesizer500 0001500 000
Unplanned expenses360 5001360 500
Total7 530 000

Expenditures of the Ministry of Urban Development currently carried out

Basement ventilation and general heating system of the church9 000 00019 000 000