Landscaping and furnishing of the basement of the church of the Holy Mother of God in Stepanakert
The church of the Holy Mother of God in Stepanakert of the Artsakh Diocese has a large basement, which served as a refuge for people during the last Artsakh war.
The room was not previously used, but served mainly as a warehouse.
We plan to improve and furnish this building with appropriate means so that it serves the spiritual, pastoral and preaching purposes of the Artsakh Diocese.
If the premises are suitable, meetings of the youth union, the women's union of the Holy Mother of God, as well as spiritual social events will be held there.
The premises will also serve for the Center for Christian Education and Propaganda of the diocese:
- Implementation of spiritual, socio-psychological, religious-moral, national-spiritual, Christian propaganda activities with various social groups in the Republic of Artsakh,
- organization of spiritual film screenings and discussions,
- to create conditions in the indicated premises so that during the liturgy mothers with young children participating in the liturgy can leave their children in the care of a nanny or educator so that they can fully participate in the liturgy,
- one of the rooms adjacent to the basement will become the diocese's library, which is currently not functioning due to lack of sufficient comfortable space,
- organize youth spiritual and religious intellectual contests and games,
- organize spiritual singing lessons,
- organize training of national dances,
- etc.
Financial expenses for the improvement and furnishing of the basement of the church of the Holy Mother of God in Stepanakert amount to AMD 7,530,000:
ESTIMATE
Furnishing and operation of the basement of the church of the Holy Mother of God | |||
---|---|---|---|
Name | Cost | Amount | Sum |
Wooden door | 200 000 | 6 | 1 200 000 |
Door installation | 15 000 | 6 | 90 000 |
Iron/soft chairs | 15 000 | 100 | 1 500 000 |
Transportation of chairs from Yerevan | 150 000 | 1 | 150 000 |
Lighting | 300 000 | 1 | 300 000 |
Audio Electronics | 1 122 500 | 1 | 1 122 500 |
Projector | 838 000 | 1 | 838 000 |
Installation of the projector and lighting fixtures on the ceiling and walls | 100 000 | 1 | 100 000 |
Tribune | 200 000 | 1 | 200 000 |
Microphone for wired case | 100 000 | 5 | 500 000 |
Flag | 60 000 | 2 | 120 000 |
Carpet | 190 000 | 2 | 380 000 |
Path | 13 000 | 13 | 169 000 |
Synthesizer | 500 000 | 1 | 500 000 |
Unplanned expenses | 360 500 | 1 | 360 500 |
Total | 7 530 000 | ||
Expenditures of the Ministry of Urban Development currently carried out | |||
Basement ventilation and general heating system of the church | 9 000 000 | 1 | 9 000 000 |